![Round Mountain Mine Phase W](https://m-m.net/wp-content/uploads/2023/01/230120-fi-round-mountain-1600x471.jpg)
Round Mountain Mine Phase W
Top-to-Bottom Design
The Round Mountain site is an open-pit mine located in Nevada, one of the best mining districts in the world. It uses conventional open-pit mining methods and processes ore by mill and heap leach.
Kinross Gold proposed needed a significant mine pit expansion to the west of the original Round Mountain mine. In order to accomplish this 1,200-foot pushback the mine’s existing infrastructure needed to be relocated, including a secondary crusher, wash bay, truck shop, warehouse, mine operations building, and fuel island. In addition, Kinross needed a new heap leach pad to accommodate ore generated from the new mine pit expansion. To maximize space and improve efficiency, Kinross also needed a new solution processing facility—a Vertical Carbon-in-Column plant (VCIC)—to support this new heap leach pad.
Using nearly all of Morrison-Maierle’s capabilities, the team provided detailed engineering for nearly all of the infrastructure and processing needs on this project.
Services & Highlights
-
Civil, structural, process, mechanical, HVAC, electrical, and instrumentation and controls engineering.
-
On-site construction quality assurance
-
New secondary crusher design
-
Design and construction of new wash bay
-
Truck shop design
-
New warehouse and mine operations building
-
New fuel island
-
New heap leach pad
-
New Vertical Carbon-in-Column (VCIC) solution processing plant
![](https://m-m.net/wp-content/uploads/2023/01/230120-pl-round-mountain-1.jpg)
![](https://m-m.net/wp-content/uploads/2023/01/230120-pq-roundmountain-003.jpg)
![](https://m-m.net/wp-content/uploads/2023/01/230120-pq-round-mountain-02.jpg)
![](https://m-m.net/wp-content/uploads/2023/01/230120-pq-round-mountain-01.jpg)
These included the truck shop, warehouse, lube room, wash bays, mine operations building, fuel islands, wet and dry utilities, and VCIC plant which cut the required footprint by nearly 60% and saved Kinross $2 million in concrete and building materials.
The expansion also included site grading and drainage to support the new facilities. Certain design elements were accelerated to support the procurement of long-lead items or long-duration construction. These included pre-engineered metal buildings, process pumps, variable frequency drives, and an electrical house. Morrison-Maierle focused early design efforts on these elements to support the supply chain, ensuring the timely arrival of construction items.
The design team produced an early set of Issue-for-Bid documents that enabled the general contractor to go under contract concurrent with the release of Issue-for-Construction documents. Over 4,000 pages of technical specifications, 602 drawings, 30,769 person-hours, and 62 personnel were involved in this project. The detailed design was completed in May 2018.
This fast-tracked project delivered a solution that used all of Morrison-Maierle’s engineering disciplines, from cost-saving building features to measures to ensure energy efficiency and sustainability.