For roughly four decades, the primary concrete runway at the Gillette Airport (Northeast Wyoming Regional Airport) has carried commercial airline service, business and corporate aviation, emergency operations, and general aviation to and from Gillette, Wyoming. After years of wear, failing panels, aging joint seals, and poor shoulder drainage, the pavement on Runway 16/34, which users depend on, was threatened.
Action was needed before small problems became large ones. Left alone, deterioration would have continued, leading to more frequent repairs and the risk of prolonged, uncertain runway closures. Because Runway 16/34 is the airport’s primary runway, any closure meant suspending commercial airline service to the community. The barriers were significant: the project’s anticipated funding fell from approximately $12 million to $5 million after the FAA determined it would not support complete reconstruction or an asphalt overlay, and the work still had to fit within a carefully coordinated airline closure.
Morrison-Maierle helped the airport deliver a focused rehabilitation that addressed its highest-priority needs. The $3+ million project was completed under budget, and the runway reopened on Day 43, two days earlier than the planned 45-day closure.
Engineering Services – Morrison-Maierle provided airport engineering for the runway rehabilitation from pre-design programming and design through construction administration and project closeout.
Rehabilitation Scope – The project replaced approximately 90 failing concrete panels, renewed more than 150,000 linear feet of joint sealant, completed approximately 1,000 sq. ft. of spall repairs, and reshaped runway shoulders to improve drainage, for just over $3 million against a $5 million funding limit. The reduced $5 million budget defined what could be built. Rather than losing the project, the team matched the scope to the funding, and the final cost came in well below that limit. Every dollar went to the pavement’s most critical needs.
Planning and Schedule – Suspending commercial airline service to Gillette was unavoidable, so the closure had to be short, predictable, and well communicated. The Airport, Morrison-Maierle, and United Airlines began planning nearly two years to select a construction window that minimized impacts on passengers and the community. Bidding in 2025 for an April 2026 start gave the Airport, engineer, and Powder River Construction several months to align on sequencing, material procurement, staffing, and schedules. During construction, close communication enabled quick resolution of field conditions, and the runway reopened on Day 43.
The Runway 16/34 Rehabilitation Project was years in the making. In 2022, the airport evaluated three alternatives: complete reconstruction, rehabilitation consisting of joint, spall, and selective panel repairs, or an asphalt overlay of the existing concrete. When the FAA declined to support reconstruction or an overlay, the airport briefly considered delaying the project until a much later date.
Instead, Morrison-Maierle’s team met with the airport and proposed a maintenance-based approach. The runway’s pavement condition index had remained strong despite its age, so the team directed limited funding to where it would do the most good. They proposed replacing severely deteriorated panels, repairing spalled concrete, renewing the joint seal system, and preserving serviceable concrete.
Drainage was a key part of the fix. Turf along the runway edges sat up to an inch above the pavement in places, allowing the shoulders to act as a dam and water to back up onto the runway. Grading the shoulders and replacing joint seals created positive drainage, directing runoff through the joints and away from the pavement.
Meet Our Airport Team
The completed rehabilitation gives Gillette a safer and more reliable primary runway supporting commercial airline service, business and corporate aviation, emergency operations, and general aviation. By addressing deterioration now, the airport extended the service life of a critical transportation asset serving Gillette, Campbell County, and northeast Wyoming.
The project also demonstrates responsible stewardship of airport funding. What began as a $12 million concept became a focused solution that preserved a runway with roughly four decades of service and delivered lasting value within a reduced budget. Careful planning balanced a significant short-term disruption with a long-term benefit to the region.
Most of all, the project shows what early coordination and teamwork can achieve. The 43 days of construction were made possible by years of evaluation, planning, and collaboration among the airport, the engineer, the airline, and the contractor.
Team Recieves 2026 Airport of the Year Project
Working around the clock for over 127 hours, Morrison-Maierle and Schellinger Construction oversaw the repaving of Missoula Montana Airport runway 12-30.
In the latest remodel, the Sheridan County Airport hired Morrison-Maierle and QC10 Architects to help with a rehabilitation and expansion project.
Alkali-Silica Reaction (ASR) is a chemical reaction in concrete that causes it to explode. ASR had not been seen in Montana until Morrison-Maierle discovered it at the Billings airport.
After planning sessions and exploring several options, the Redmond Airport built a new 45,000 sq. ft. snow-removal and equipment facility that could serve many purposes.
The Missoula Montana Airport hired Morrison-Maierle to complete a comprehensive runway survey using LiDAR scanning.
The Missoula Montana Airport hired Morrison-Maierle to help design their new passenger terminal. The new building increased airline capacity and improved safety and security for the airport.
The Deer Lodge City–County Airport Improvements Project condensed what had been anticipated as a four-year effort into two-years and secured nearly $14M in federal and state funds.
Charter Realty & Development hired Morrison-Maierle to help them redevelop the Yellowstone Airport Plaza next to the East Belgrade Interchange near Bozeman.
Bozeman Yellowstone Airport Parking Garage
The Gallatin Airport Authority hired Morrison-Maierle to assist with the Bozeman Yellowstone International Airport (BZN) Inline Baggage System update project.
Thirty years after its last remodel, the Billings Logan International Airport hired Morrison-Maierle to help update and expand its terminal building.
Billings-Logan International Airport needed a solution to control the large stormwater events on the airfield, put the water in a new pond structure, and drain them to a creek.
Morrison-Maierle was the prime consultant on this project and was hired to design the site civil, mechanical, electrical, plumbing, and structural engineering for the Bert Mooney Airport.
The new 100-foot air traffic control tower at the Bend Municipal Airport improves flight safety and operations with a resilient, seismically designed, fully integrated facility.
We know that building great communities starts with teams made up of great people. If you’re exploring ways to collaborate and make an impact, join us.
Explore Career Opportunities